CIMS: one auditable record for every household affected by a water pipeline

For the AfDB-financed Lesotho Lowlands Water Development Project Phase III, CIMS replaced paper files and spreadsheet reconciliation with a single, secure system of record for compensating Project Affected Persons.

Water infrastructure in the Lesotho lowlands
Client
Ministry of Natural Resources — LLWDP III PIU
Financing
African Development Bank
Role
Design, build and operate
Live at
cims.4dcs.co.za
1,405affected households registered
93%verified and approved
155with payment recorded
24pipeline routes (16 rural · 8 urban)

Live production data, September 2026.

The challenge

Compensation for land and assets along pipeline routes involves thousands of households, official rates, photos, IDs, signed agreements and payments — and every figure must stand up to audit and to the community. Paper files and spreadsheets drift, duplicate and dispute.

What we did

  • Built a household and asset registry linking beneficiaries, co-owners, land, structures, trees, crops and communal assets
  • Made a central Rates Master the single source for every compensation calculation
  • Put every edit through an edit-request and approval chain, with a change history on each record
  • Added print-ready verification forms, field document capture and payment tracking
  • Onboarded the full field and liaison team — from two users to 19 active staff accounts in four months

How it's built

React SPAPostgreSQL with row-level securityEncrypted document storageRole-based access across nine staff roles